Preloader Close

HON. KHODHE PHELIX ODIWUOR

Constituency: Lang'ata

His Excellency Hon. Phelix Odiwuor, popularly known as Jalang’o, is a Kenyan politician, media personality, and entrepreneur. Born on April 27, 1983, in Homa Bay County, he rose to fame as a comedian and radio host, gaining prominence in the entertainment industry. Jalang’o ventured into politics and was elected Member of Parliament for Lang’ata Constituency […]

His Excellency Hon. Phelix Odiwuor, popularly known as Jalang’o, is a Kenyan politician, media personality, and entrepreneur. Born on April 27, 1983, in Homa Bay County, he rose to fame as a comedian and radio host, gaining prominence in the entertainment industry. Jalang’o ventured into politics and was elected Member of Parliament for Lang’ata Constituency in 2022 under the Orange Democratic Movement (ODM) party. His political agenda emphasizes education, youth empowerment, and infrastructure development. Jalang’o’s transition from entertainment to politics reflects his commitment to serving his community.


Educational Background

From

To

Institution

Qualification

2014

2018

Daystar University

B.A Community Developments

1998

2001

Nyangoma Boys Secondary School

KCSE

1990

1997

Lake Primary School- Homabay

KCPE

Work Experience

From

To

Employer

Position held

2020

2022

Radio Africa Group

Radio Host

2018

2020

Mediamax Network Ltd

Radio Host

2017

2018

Royal Media Services

Radio Host

2013

2017

Standard Group

Radio Host

2007

2013

Radio Africa Group

Radio Host

2010

2022

Arena Media

Director/CEO

Politics

Projects

Budget Managed
Revenue: KES. 99,052,635
Expenditure: KES. 74,351,149

Non-current Assets

Total Contract Amount: KES. 47,690,025
Amount of Money Paid: KES. 47,690,025
% Age Payment: 100%
Status of the Project: Not done. Funds of KES.10,290,025 was transferred to other Government units but projects were not executed. No value for money confirmed on the amount spent.

Location: Kongoni Secondary School
Total Contract Amount: KES.92,417,657
Amount of Money Paid: KES. 28,095,746 (initial contractor) + KES. 4,611,252 (new contractor) = KES. 32,706,998
% Age Payment: 35.4%
Status of the Project: Incomplete The contractor’s performance bond expired before the last payment. 50% of retention money was released without justification. A new contractor was hired directly without proper procurement procedures. The new contractor received KES. 4,611,252, but there was no proof of additional work done. Physical inspection in March 2024 confirmed that the project was abandoned. Violations of the Public Procurement and Asset Disposal Act, 2015

Citizen’s Performance Score Card

5
Select your rating of their performance

Educational Background

From

To

Institution

Qualification

2014

2018

Daystar University

B.A Community Developments

1998

2001

Nyangoma Boys Secondary School

KCSE

1990

1997

Lake Primary School- Homabay

KCPE

Work Experience

From

To

Employer

Position held

2020

2022

Radio Africa Group

Radio Host

2018

2020

Mediamax Network Ltd

Radio Host

2017

2018

Royal Media Services

Radio Host

2013

2017

Standard Group

Radio Host

2007

2013

Radio Africa Group

Radio Host

2010

2022

Arena Media

Director/CEO

Politics

Projects

Budget Managed
Revenue: KES. 99,052,635
Expenditure: KES. 74,351,149

Non-current Assets

Total Contract Amount: KES. 47,690,025
Amount of Money Paid: KES. 47,690,025
% Age Payment: 100%
Status of the Project: Not done. Funds of KES.10,290,025 was transferred to other Government units but projects were not executed. No value for money confirmed on the amount spent.

Location: Kongoni Secondary School
Total Contract Amount: KES.92,417,657
Amount of Money Paid: KES. 28,095,746 (initial contractor) + KES. 4,611,252 (new contractor) = KES. 32,706,998
% Age Payment: 35.4%
Status of the Project: Incomplete The contractor’s performance bond expired before the last payment. 50% of retention money was released without justification. A new contractor was hired directly without proper procurement procedures. The new contractor received KES. 4,611,252, but there was no proof of additional work done. Physical inspection in March 2024 confirmed that the project was abandoned. Violations of the Public Procurement and Asset Disposal Act, 2015

Citizen’s Performance Score Card

5
Select your rating of their performance